1. Choose the demand period. Use one shift, day, campaign, or another consistent planning window.
2. Enter net available time. Subtract planned nonproduction time before entering minutes when that time cannot be used to make output.
3. Enter required packages. Use the demand that must be completed in the same period.
4. Read the takt time. The main result is the average time available for each required package.
5. Compare with cycle time. If expected cycle time is longer than takt time, the planned process may not meet demand without changes.