1. Enter total footing volume
Use the full concrete volume assigned to the footing activity.
2. Set expected daily placement
Enter a realistic average daily output for the crew, including the interruptions you expect to occur during normal production.
3. Add fixed nonproduction days
Include mobilization, layout, planned setup, or other known time that does not scale with volume.
4. Choose the workweek
Specify how many days per week the footing operation is expected to run.
5. Read working days and calendar weeks
Use working days for activity duration and calendar weeks for a higher-level schedule check.