1. Enter deck size
Use the finished deck length and width to establish project area.
2. Set baseline productivity
Enter the square feet one worker can complete per labor-hour for a relatively straightforward version of the project.
3. Add a complexity allowance
Increase labor for stairs, railings, elevation, difficult access, intricate layouts, or other scope factors.
4. Enter crew size
Use the number of workers expected to be actively assigned to the deck.
5. Set workday length
Choose the planned working hours per person per day.
6. Review total labor and crew days
Use labor-hours for estimating and crew days for schedule planning, then add non-working delays separately.